CASE STUDY
Customer: National Drug Store Chain
Project
When one of the largest and fastest-growing retailers in the world stepped up their energy savings initiatives, they turned to Wesco for a turnkey solution and streamlined execution. With a wide variety of store layouts and existing lighting technologies in place, the project presented complex challenges of project management and product selection. The project’s overwhelming success demonstrates why leading retailers consider Wesco as the ultimate resource for reducing their energy and maintenance costs.
Solutions
To meet the enormous scale of this project, the Wesco team provided full project management services, including:
- Store surveys and audits
- Material stocking and distribution
- Work scheduling with local store managers
- Permit application and approval
- Sub-contractor management
We also delivered a streamlined rebate and proposal process, created new standards in customer service, and accelerated execution. To handle the large number of simultaneous retrofits, we established dedicated product warehouses and secured additional suppliers to ensure uninterrupted supplies.
Results
- 10,179 total projects since 2011
- Energy savings: 1.4 billion kwh
- Energy cost savings: $56.2 million
- Rebates received from2011-2020: $18.73m
- Average payback: <3 years
- Reduced 992,722 metric tons of CO2 (equivalent of removing 215,897 cars from the road)
This drug store chain continues to expand with new stores, as well as upgrading existing stores. Wesco remains one of their top partners for lighting and full turnkey services.